THE COMPLETION OF THE NEW WOODBURY COUNTY LAW ENFORCEMENT CENTER WILL APPARENTLY NOW NOT HAPPEN UNTIL THE SUMMER.
L-E-C AUTHORITY CHAIRMAN RON WIECK ISSUED A STATEMENT ON THE ONGOING CONSTRUCTION AND DELAYS TO LOCAL MEDIA ON TUESDAY:
LECDELAY1 OC………COSTS AND DAMAGES. :35
WIECK EXPLAINED THAT THE NEW DELAYS INVOLVED A VARIETY OF MECHANICAL ISSUES REGARDING FIVE FAN POWERED BOXES AND FIVE CONTROL VALVES THAT NEEDED TO BE CHANGED, NEEDED PARTS THAT STILL HAVEN’T ARRIVED, AND OTHER ISSUES:
LECDELAY2 OC……INTROBA. ;24