Home Local News MYRTLE STREET RECONSTRUCTION TO RESUME NEXT WEEK

MYRTLE STREET RECONSTRUCTION TO RESUME NEXT WEEK

896
SHARE

THE NEXT PHASE OF THE MYRTLE STREET RECONSTRUCTION PROJECT ON SIOUX CITY’S NORTHWEST SIDE WILL BEGIN NEXT MONDAY, MARCH 29TH.

THE PROJECT WILL RECONSTRUCT THE ROADWAY AND SIDEWALKS ON MYRTLE STREET FROM JUST SOUTH OF WEST 26TH STREET TO WEST CLIFTON STREET.

CITY UTILITIES SUCH AS WATER, STORM AND SANITARY SEWER WILL ALSO BE REPLACED.

THE REMAINDER OF THE PROJECT WILL BE COMPLETED IN THREE PHASES.

THE FIRST STAGE WILL CONSTRUCT THE REMAINDER OF THE WATER MAIN FROM THE END OF THE 2020 CONSTRUCTION SEASON TO WEST CLIFTON BOULEVARD.

THE SECOND STAGE WILL CLOSE MYRTLE STREET BETWEEN WEST 28TH STREET AND WEST 31ST STREET.

THE THIRD AND FINAL STAGE WILL CLOSE MYRTLE STREET BETWEEN WEST 31ST STREET AND WEST CLIFTON STREET.

THE WORK IS ANTICIPATED TO BE COMPLETE THIS CONSTRUCTION SEASON.