Home Local News MORNINGSIDE AVENUE WORK SHIFTS TO PHASE TWO

MORNINGSIDE AVENUE WORK SHIFTS TO PHASE TWO

3294
0
SHARE

PHASE TWO OF THE RECONSTRUCTION OF PART OF MORNINGSIDE AVENUE IN THE PETERS PARK AREA WILL BEGIN ON WEDNESDAY.

THE CITY’S ENGINEERING DEPARTMENT SAYS WORK WILL SHIFT FROM THE NORTH SIDE OF THE STREET ACROSS TO THE SOUTH SIDE OF THE AVENUE BETWEEN SOUTH ROYCE TO SOUTH NICOLLET STREETS.

TRAFFIC WILL BE ONE LANE IN EACH DIRECTION IN THAT SECTION OF THE AVENUE.

SIDEWALK PAVING WILL ALSO TAKE PLACE AND ACCESS TO BUSINESSES WILL BE MAINTAINED.

THE PROJECT IS SET TO BE COMPLETED BY NOVEMBER 21ST.